Step 9: Approvals & Construction

step 9

Before major construction can begin, the District will need to obtain a considerable number of required approvals and inspections. This work, including environmental impact reports and submission of plans to the Division of the State Architect (DSA), could easily stretch 6 to 9 months into Winter 2020. 

All efforts will be made to coordinate pre-construction and student housing needs so that construction can start the day after summer dismissal June 2021. In this scenario, construction takes place June 2021 through August 2022 for Ormondale and February 2023 for Corte Madera. This would limit the impact of construction on classroom learning to just over one school year.